Budget
Project Budget
All Monetary Figures in US dollars :
1. How Much Will It Cost To Build The Biogas Project? $549,440.00
Construction Costs | |
Solar Array Material Only | $23,800.00 |
Batteries Material Only | $32,950.00 |
Solar Array and Batteries Labor and Transportation | $30,250.00 |
Digester | $40,650.00 |
Building and Septic | $390,690.00 |
SUBTOTAL | $518,340.00 |
Miscellaneous @ 6% | $31,100.00 |
TOTAL | $549,440.00 |
Show Us You Care About Stopping This Pollution
2. How Much Will It Cost To Operate The Biogas Project?
A. Initial operations and maintenance: For the first 2 years, before handover to the Nepal Government: | $82,000.00 |
Salary and living expenses for 3 Nepali operators to run the biogas system: $600 per month per person |
$21,600.00 |
Consulting consortium expenses to support the operators consisting of members from: Biogas Project personnel: Trip expenses to Gorak Shep. |
No Salary |
3 trips/yr X $2,850/trip | $8,550.00 |
Seattle University personnel | No Salary. |
2 trips/yr X $2,850/trip | $5,700.00 |
Kathmandu University personnel: Trip expenses to Gorak Shep | No Salary |
3 trips/yr X $1,150/trip | $3,450.00 |
Biogas Sector Partnership-Nepal personnel: Trip expenses and salary to Gorak Shep | |
1 trip/yr X $1,700/trip | $1,700.00 |
Total 1 year cost: initial operations and maintenance: | $41,000.00 |
For the first 2 years, before handover to the Nepal Government | $82,000.00 for the first 2 years. |
B. After The Project is Completed and Tested, It Will Be Handed Over To The Local Nepalese Government and They Will Run It. | |
Annual Cost to Run the Project: | $34,700.00 per year. |
Salary and living expenses for 3 Nepali operators to run the biogas system: $600 per month per person x 3 operators x 1 yr: | $21,600.00 |
Nepal Government staff person, technically trained in Everest Biogas technology, based in Namche. | $6750.00 per year |
Estimated equipment maintenance and operations budget: | $5200.00 per year |
Annual Consulting Consortium costs to support the operators: | $1150.00 per year |
Total per year to operate the project | $34,700.00 |